NGCP SCHEDULED POWER INTERRUPTION

WHEN: February 5, 2022 (Saturday); 6:00AM – 6:00PM (12 Hours)

AFFECTED AREAS: Whole Coverage Area of Calatrava , and San Carlos

SUBSTATION AFFECTED: 5MVA Calatrava – Toboso Substation, 20MVA San Carlos Substation

REASON : NGCP Contractor will conduct wire stringing activities of Calatrava- San Carlos 69kV line.

NONECO 20MVA San Carlos Substation will be load shift to Guihulngan 69kV Transmission line to minimize power interruption in Calatrava, and San Carlos.

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

WHEN: February 5, 2022 (Saturday); 8:00AM – 5:00PM (9 Hours)

AFFECTED AREAS: Whole Coverage Area of Escalante

SUBSTATION AFFECTED: 10MVA Escalante Substation

REASON: Rehabilitation and construction of double circuit distribution line from Brgy. Jonob-Jonob to Escalante Rotonda that will contribute to Power Quality and Reliability improvement.