NOTICE OF NGCP MANUAL LOAD DROPPING
NGCP may implement Manual Load Dropping (MLD) today, March 31, 2022 starting 6:00PM in the franchise areas of NONECO
6:00 PM – 4.4 MW
7:00 PM – 4.4 MW
8:00 PM – 4.4 MW
As per NGCP, a contingency measure to prevent the overloading of the 138 kv Samboan-Amlan line 2, Emergency shutdown of PCPC and plan outage of PGPP1 U1.
MLD is projected to last until 9:00PM or earlier. Schedule may be cancelled if system condition improves.
We apologize for the inconvenience caused by this. Thank you for your cooperation.